Pavilion date set

August 4, 2023 BY

Council says it understands the frustrations of the community, but will have the Ballan pavilion complete next month. Photo – Moorabool Shire Council

Frustrations have been bubbling over a delayed pavilion project in Ballan, but Moorabool Shire Council says it will be completed next month.

Last week, Council announced that the Ballan Recreation Reserve pavilion was due for completion in late September. The first sod was turned for the project in February 2022, with the initial completion date at that time announced as November 2022.

Reasons for delays to the project have included slow progress with the original demolition contractor, poor weather, and delays obtaining a permit for installation of underground services.

But Council now says the pavilion will be fully operational for the start of the cricket season.

Council CEO Derek Madden said the delays in the project were disappointing, but everyone was looking forward to being able to use the brand new facility soon.

“Ballan Football and Netball Club has chosen not to use the ground for their home games this season even though they have been able to access the new changerooms for a few months, so we have been working with them to source alternate venues,” Mr Madden said.

“They have been training at the ground, and we hope they’re looking forward to a big season in their new facility in 2024.

“Ballan Cricket Club will be able to make great use of the new changerooms and social pavilion for their 2024 season. In addition, there are new cricket training nets at the site, so local cricketers will have the best facilities from this season on. There will soon be a new electronic scoreboard at the ground, funded under Council’s latest round of community grants.”

Council is working closely with the Ballan Football and Netball Club with monthly in-person committee meetings and regular emails to keep them up to date with progress.

“We understand the club has been frustrated with the delays, as has everyone involved, but we will deliver a fantastic modern facility that will carry the user groups and the community into the future, which is exciting for Ballan and surrounds,” Mr Madden said.