	{"id":11286,"date":"2022-08-18T08:00:20","date_gmt":"2022-08-17T22:00:20","guid":{"rendered":"https:\/\/themooraboolnews.com.au\/?p=11286"},"modified":"2024-02-02T22:12:50","modified_gmt":"2024-02-02T11:12:50","slug":"pavilion-delays-cause-frustration","status":"publish","type":"post","link":"https:\/\/timesnewsgroup.com.au\/themooraboolnews\/news\/pavilion-delays-cause-frustration\/","title":{"rendered":"Pavilion delays cause frustration"},"content":{"rendered":"<p>By Lachlan Ellis<\/p>\n<p>Two major projects for Moorabool sporting clubs have had their completion dates pushed back until 2023, with a range of complications including material supply problems and workforce shortages blamed.<br \/>\nMoorabool Shire Council CEO Derek Madden said the delays for the Ballan Recreation Reserve and the Darley Park Pavilion were frustrating, and several issues were responsible.<br \/>\n\u201cCouncil is disappointed that progress on these two projects has been slower than expected, but we understand the challenges the construction industry faces with material supply issues, workforce limitations and availability of specialised tradespeople,\u201d Mr Madden told the Moorabool News.<br \/>\n\u201cProgress with the new Ballan Recreation Reserve Pavilion has been impacted by a number of issues. These include slow progress with the original demolition contractor in January\/February 2022 which required Council to make alternative arrangements with the nominated building contractor to compete the demolition works.\u201d<br \/>\nMr Madden said there were also delays with obtaining a permit from Central Highlands Water for installation of underground services.<br \/>\n\u201cThese delays pushed the concrete slab construction into the winter period with consequent challenges due to adverse weather.\u201d<br \/>\nAnd with Darley Park Pavilion, Mr Madden said delays have been caused by a number of compliance concerns regarding the future building and the existing building.<br \/>\n\u201cThis has required a number of trades to be repriced and procured, and with the amount of work occurring within the industry, it has led to recommencement of work, which is taking longer than expected.\u201d<br \/>\nPeter McGregor is President of the Ballan Recreation Reserve Committee of Management, and said the delays were disappointing for those that use the Reserve, but he hoped to see the works done early next year.<br \/>\n\u201cFor users it\u2019s frustrating, but then we\u2019ve also had some exceptional circumstances this financial year as well. I imagine the Cricket Club will be most affected [with the timing], but I\u2019m pushing for them to finish the works as early as possible, and hopefully they can hold some major functions towards the end of the season, which will help them get back on track,\u201d Mr McGregor said.<br \/>\n\u201cAs for the ground itself, they should be able to use it. It\u2019s just limited for social functions at this stage. I\u2019ve had a lot of discussions with a representative from Council, there was a period of time where they couldn\u2019t tell us much, but I believe they\u2019re now getting back on track. There\u2019s been a combination of issues, but I think the Council\u2019s getting back on top of them.\u201d<br \/>\nMember for Buninyong, Michaela Settle \u2013 was present at the first sod turnings at Ballan in February and Darley in March \u2013 said she had been checking in with Council on the Ballan project.<br \/>\n&#8220;I can&#8217;t wait to see the Ballan Recreation Reserve Hub completed and have spoken regularly with Council to track progress. I know that the Council has been working closely with the local contractor to make sure the project is finished in plenty of time for the footy season. This will be a great community space for everyone in Ballan,\u201d Ms Settle said.<br \/>\nThe contract for Ballan Recreation Reserve Pavilion was awarded to WP Contractors in January 2022, and the contract for Darley Reserve Pavilion was awarded to Midson Constructions in October 2021.<br \/>\nThe original planned completion date for both projects was November 2022, but the current date for completion is now February\/March 2023.<br \/>\nA Council spokesperson said the delays would not have cost implications for Council, with both pavilions to be \u201cdelivered within budget\u201d.<br \/>\nWP Contractors were contacted for comment but did not respond.<\/p>\n","protected":false},"excerpt":{"rendered":"<p>By Lachlan Ellis Two major projects for Moorabool sporting clubs have had their completion dates pushed back until 2023, with a range of complications including material supply problems and workforce shortages blamed. Moorabool Shire Council CEO Derek Madden said the delays for the Ballan Recreation Reserve and the Darley Park Pavilion were frustrating, and several [&#8230;]<\/p>\n<p><a class=\"btn btn-secondary understrap-read-more-link\" href=\"https:\/\/timesnewsgroup.com.au\/themooraboolnews\/news\/pavilion-delays-cause-frustration\/\">Read More&#8230;<\/a><\/p>\n","protected":false},"author":221,"featured_media":25815,"comment_status":"closed","ping_status":"closed","sticky":false,"template":"","format":"standard","meta":{"_acf_changed":false,"inline_featured_image":false,"footnotes":""},"categories":[15],"tags":[6552,2308,31,73,33,6553],"post_folder":[],"class_list":["post-11286","post","type-post","status-publish","format-standard","has-post-thumbnail","hentry","category-news","tag-ballan-rec-reserve","tag-darley-park","tag-derek-madden","tag-michaela-settle","tag-moorabool-shire-council","tag-pavilion-delays"],"acf":[],"yoast_head":"<!-- This site is optimized with the Yoast SEO plugin v27.7 - https:\/\/yoast.com\/product\/yoast-seo-wordpress\/ -->\n<title>Pavilion delays cause frustration - The Moorabool News<\/title>\n<meta name=\"robots\" content=\"index, follow, max-snippet:-1, max-image-preview:large, max-video-preview:-1\" \/>\n<link rel=\"canonical\" href=\"https:\/\/timesnewsgroup.com.au\/themooraboolnews\/news\/pavilion-delays-cause-frustration\/\" \/>\n<meta property=\"og:locale\" content=\"en_US\" \/>\n<meta property=\"og:type\" content=\"article\" \/>\n<meta property=\"og:title\" content=\"Pavilion delays cause frustration - The Moorabool News\" \/>\n<meta property=\"og:description\" content=\"By Lachlan Ellis Two major projects for Moorabool sporting clubs have had their completion dates pushed back until 2023, with a range of complications including material supply problems and workforce shortages blamed. Moorabool Shire Council CEO Derek Madden said the delays for the Ballan Recreation Reserve and the Darley Park Pavilion were frustrating, and several [...]Read More...\" \/>\n<meta property=\"og:url\" content=\"https:\/\/timesnewsgroup.com.au\/themooraboolnews\/news\/pavilion-delays-cause-frustration\/\" \/>\n<meta property=\"og:site_name\" content=\"The Moorabool News\" \/>\n<meta property=\"article:published_time\" content=\"2022-08-17T22:00:20+00:00\" \/>\n<meta property=\"article:modified_time\" content=\"2024-02-02T11:12:50+00:00\" \/>\n<meta property=\"og:image\" content=\"https:\/\/static.timesnewsgroup.com.au\/prod\/uploads\/sites\/28\/2022\/08\/website-640x480-1.jpg\" \/>\n\t<meta property=\"og:image:width\" content=\"640\" \/>\n\t<meta property=\"og:image:height\" content=\"480\" \/>\n\t<meta property=\"og:image:type\" content=\"image\/jpeg\" \/>\n<meta name=\"author\" content=\"Lachlan Ellis\" \/>\n<meta name=\"twitter:card\" content=\"summary_large_image\" \/>\n<meta name=\"twitter:label1\" content=\"Written by\" \/>\n\t<meta name=\"twitter:data1\" content=\"Lachlan Ellis\" \/>\n\t<meta name=\"twitter:label2\" content=\"Est. reading time\" \/>\n\t<meta name=\"twitter:data2\" content=\"3 minutes\" \/>\n<script type=\"application\/ld+json\" class=\"yoast-schema-graph\">{\"@context\":\"https:\\\/\\\/schema.org\",\"@graph\":[{\"@type\":\"Article\",\"@id\":\"https:\\\/\\\/timesnewsgroup.com.au\\\/themooraboolnews\\\/news\\\/pavilion-delays-cause-frustration\\\/#article\",\"isPartOf\":{\"@id\":\"https:\\\/\\\/timesnewsgroup.com.au\\\/themooraboolnews\\\/news\\\/pavilion-delays-cause-frustration\\\/\"},\"author\":{\"name\":\"Lachlan Ellis\",\"@id\":\"https:\\\/\\\/timesnewsgroup.com.au\\\/themooraboolnews\\\/#\\\/schema\\\/person\\\/bfbc5a1c6baaf34dd181f21c64f18302\"},\"headline\":\"Pavilion delays cause frustration\",\"datePublished\":\"2022-08-17T22:00:20+00:00\",\"dateModified\":\"2024-02-02T11:12:50+00:00\",\"mainEntityOfPage\":{\"@id\":\"https:\\\/\\\/timesnewsgroup.com.au\\\/themooraboolnews\\\/news\\\/pavilion-delays-cause-frustration\\\/\"},\"wordCount\":600,\"publisher\":{\"@id\":\"https:\\\/\\\/timesnewsgroup.com.au\\\/themooraboolnews\\\/#organization\"},\"image\":{\"@id\":\"https:\\\/\\\/timesnewsgroup.com.au\\\/themooraboolnews\\\/news\\\/pavilion-delays-cause-frustration\\\/#primaryimage\"},\"thumbnailUrl\":\"https:\\\/\\\/static.timesnewsgroup.com.au\\\/prod\\\/uploads\\\/sites\\\/28\\\/2022\\\/08\\\/website-640x480-1.jpg\",\"keywords\":[\"ballan rec reserve\",\"darley park\",\"derek madden\",\"michaela settle\",\"Moorabool Shire Council\",\"pavilion delays\"],\"articleSection\":[\"News\"],\"inLanguage\":\"en-AU\"},{\"@type\":\"WebPage\",\"@id\":\"https:\\\/\\\/timesnewsgroup.com.au\\\/themooraboolnews\\\/news\\\/pavilion-delays-cause-frustration\\\/\",\"url\":\"https:\\\/\\\/timesnewsgroup.com.au\\\/themooraboolnews\\\/news\\\/pavilion-delays-cause-frustration\\\/\",\"name\":\"Pavilion delays cause frustration - The Moorabool News\",\"isPartOf\":{\"@id\":\"https:\\\/\\\/timesnewsgroup.com.au\\\/themooraboolnews\\\/#website\"},\"primaryImageOfPage\":{\"@id\":\"https:\\\/\\\/timesnewsgroup.com.au\\\/themooraboolnews\\\/news\\\/pavilion-delays-cause-frustration\\\/#primaryimage\"},\"image\":{\"@id\":\"https:\\\/\\\/timesnewsgroup.com.au\\\/themooraboolnews\\\/news\\\/pavilion-delays-cause-frustration\\\/#primaryimage\"},\"thumbnailUrl\":\"https:\\\/\\\/static.timesnewsgroup.com.au\\\/prod\\\/uploads\\\/sites\\\/28\\\/2022\\\/08\\\/website-640x480-1.jpg\",\"datePublished\":\"2022-08-17T22:00:20+00:00\",\"dateModified\":\"2024-02-02T11:12:50+00:00\",\"breadcrumb\":{\"@id\":\"https:\\\/\\\/timesnewsgroup.com.au\\\/themooraboolnews\\\/news\\\/pavilion-delays-cause-frustration\\\/#breadcrumb\"},\"inLanguage\":\"en-AU\",\"potentialAction\":[{\"@type\":\"ReadAction\",\"target\":[\"https:\\\/\\\/timesnewsgroup.com.au\\\/themooraboolnews\\\/news\\\/pavilion-delays-cause-frustration\\\/\"]}]},{\"@type\":\"ImageObject\",\"inLanguage\":\"en-AU\",\"@id\":\"https:\\\/\\\/timesnewsgroup.com.au\\\/themooraboolnews\\\/news\\\/pavilion-delays-cause-frustration\\\/#primaryimage\",\"url\":\"https:\\\/\\\/static.timesnewsgroup.com.au\\\/prod\\\/uploads\\\/sites\\\/28\\\/2022\\\/08\\\/website-640x480-1.jpg\",\"contentUrl\":\"https:\\\/\\\/static.timesnewsgroup.com.au\\\/prod\\\/uploads\\\/sites\\\/28\\\/2022\\\/08\\\/website-640x480-1.jpg\",\"width\":640,\"height\":480,\"caption\":\"Ballan Recreation Reserve works have come to a halt, before they have really started. Photo - Lachlan Ellis\"},{\"@type\":\"BreadcrumbList\",\"@id\":\"https:\\\/\\\/timesnewsgroup.com.au\\\/themooraboolnews\\\/news\\\/pavilion-delays-cause-frustration\\\/#breadcrumb\",\"itemListElement\":[{\"@type\":\"ListItem\",\"position\":1,\"name\":\"Home\",\"item\":\"https:\\\/\\\/timesnewsgroup.com.au\\\/themooraboolnews\\\/\"},{\"@type\":\"ListItem\",\"position\":2,\"name\":\"Pavilion delays cause frustration\"}]},{\"@type\":\"WebSite\",\"@id\":\"https:\\\/\\\/timesnewsgroup.com.au\\\/themooraboolnews\\\/#website\",\"url\":\"https:\\\/\\\/timesnewsgroup.com.au\\\/themooraboolnews\\\/\",\"name\":\"The Moorabool News\",\"description\":\"\",\"publisher\":{\"@id\":\"https:\\\/\\\/timesnewsgroup.com.au\\\/themooraboolnews\\\/#organization\"},\"potentialAction\":[{\"@type\":\"SearchAction\",\"target\":{\"@type\":\"EntryPoint\",\"urlTemplate\":\"https:\\\/\\\/timesnewsgroup.com.au\\\/themooraboolnews\\\/?s={search_term_string}\"},\"query-input\":{\"@type\":\"PropertyValueSpecification\",\"valueRequired\":true,\"valueName\":\"search_term_string\"}}],\"inLanguage\":\"en-AU\"},{\"@type\":\"Organization\",\"@id\":\"https:\\\/\\\/timesnewsgroup.com.au\\\/themooraboolnews\\\/#organization\",\"name\":\"The Moorabool News\",\"url\":\"https:\\\/\\\/timesnewsgroup.com.au\\\/themooraboolnews\\\/\",\"logo\":{\"@type\":\"ImageObject\",\"inLanguage\":\"en-AU\",\"@id\":\"https:\\\/\\\/timesnewsgroup.com.au\\\/themooraboolnews\\\/#\\\/schema\\\/logo\\\/image\\\/\",\"url\":\"https:\\\/\\\/static.timesnewsgroup.com.au\\\/prod\\\/uploads\\\/sites\\\/28\\\/2024\\\/01\\\/MooraboolNews-logo.png\",\"contentUrl\":\"https:\\\/\\\/static.timesnewsgroup.com.au\\\/prod\\\/uploads\\\/sites\\\/28\\\/2024\\\/01\\\/MooraboolNews-logo.png\",\"width\":1089,\"height\":400,\"caption\":\"The Moorabool News\"},\"image\":{\"@id\":\"https:\\\/\\\/timesnewsgroup.com.au\\\/themooraboolnews\\\/#\\\/schema\\\/logo\\\/image\\\/\"}},{\"@type\":\"Person\",\"@id\":\"https:\\\/\\\/timesnewsgroup.com.au\\\/themooraboolnews\\\/#\\\/schema\\\/person\\\/bfbc5a1c6baaf34dd181f21c64f18302\",\"name\":\"Lachlan Ellis\",\"image\":{\"@type\":\"ImageObject\",\"inLanguage\":\"en-AU\",\"@id\":\"https:\\\/\\\/secure.gravatar.com\\\/avatar\\\/4b8766ff6263c9ffb6ec80f89efea9b7a992bc23f7fd86445d569b0e6b510f3e?s=96&d=mm&r=g\",\"url\":\"https:\\\/\\\/secure.gravatar.com\\\/avatar\\\/4b8766ff6263c9ffb6ec80f89efea9b7a992bc23f7fd86445d569b0e6b510f3e?s=96&d=mm&r=g\",\"contentUrl\":\"https:\\\/\\\/secure.gravatar.com\\\/avatar\\\/4b8766ff6263c9ffb6ec80f89efea9b7a992bc23f7fd86445d569b0e6b510f3e?s=96&d=mm&r=g\",\"caption\":\"Lachlan Ellis\"},\"url\":\"https:\\\/\\\/timesnewsgroup.com.au\\\/themooraboolnews\\\/author\\\/lachlanellis\\\/\"}]}<\/script>\n<!-- \/ Yoast SEO plugin. -->","yoast_head_json":{"title":"Pavilion delays cause frustration - The Moorabool News","robots":{"index":"index","follow":"follow","max-snippet":"max-snippet:-1","max-image-preview":"max-image-preview:large","max-video-preview":"max-video-preview:-1"},"canonical":"https:\/\/timesnewsgroup.com.au\/themooraboolnews\/news\/pavilion-delays-cause-frustration\/","og_locale":"en_US","og_type":"article","og_title":"Pavilion delays cause frustration - The Moorabool News","og_description":"By Lachlan Ellis Two major projects for Moorabool sporting clubs have had their completion dates pushed back until 2023, with a range of complications including material supply problems and workforce shortages blamed. Moorabool Shire Council CEO Derek Madden said the delays for the Ballan Recreation Reserve and the Darley Park Pavilion were frustrating, and several [...]Read More...","og_url":"https:\/\/timesnewsgroup.com.au\/themooraboolnews\/news\/pavilion-delays-cause-frustration\/","og_site_name":"The Moorabool News","article_published_time":"2022-08-17T22:00:20+00:00","article_modified_time":"2024-02-02T11:12:50+00:00","og_image":[{"width":640,"height":480,"url":"https:\/\/static.timesnewsgroup.com.au\/prod\/uploads\/sites\/28\/2022\/08\/website-640x480-1.jpg","type":"image\/jpeg"}],"author":"Lachlan Ellis","twitter_card":"summary_large_image","twitter_misc":{"Written by":"Lachlan Ellis","Est. reading time":"3 minutes"},"schema":{"@context":"https:\/\/schema.org","@graph":[{"@type":"Article","@id":"https:\/\/timesnewsgroup.com.au\/themooraboolnews\/news\/pavilion-delays-cause-frustration\/#article","isPartOf":{"@id":"https:\/\/timesnewsgroup.com.au\/themooraboolnews\/news\/pavilion-delays-cause-frustration\/"},"author":{"name":"Lachlan Ellis","@id":"https:\/\/timesnewsgroup.com.au\/themooraboolnews\/#\/schema\/person\/bfbc5a1c6baaf34dd181f21c64f18302"},"headline":"Pavilion delays cause frustration","datePublished":"2022-08-17T22:00:20+00:00","dateModified":"2024-02-02T11:12:50+00:00","mainEntityOfPage":{"@id":"https:\/\/timesnewsgroup.com.au\/themooraboolnews\/news\/pavilion-delays-cause-frustration\/"},"wordCount":600,"publisher":{"@id":"https:\/\/timesnewsgroup.com.au\/themooraboolnews\/#organization"},"image":{"@id":"https:\/\/timesnewsgroup.com.au\/themooraboolnews\/news\/pavilion-delays-cause-frustration\/#primaryimage"},"thumbnailUrl":"https:\/\/static.timesnewsgroup.com.au\/prod\/uploads\/sites\/28\/2022\/08\/website-640x480-1.jpg","keywords":["ballan rec reserve","darley park","derek madden","michaela settle","Moorabool Shire Council","pavilion delays"],"articleSection":["News"],"inLanguage":"en-AU"},{"@type":"WebPage","@id":"https:\/\/timesnewsgroup.com.au\/themooraboolnews\/news\/pavilion-delays-cause-frustration\/","url":"https:\/\/timesnewsgroup.com.au\/themooraboolnews\/news\/pavilion-delays-cause-frustration\/","name":"Pavilion delays cause frustration - The Moorabool News","isPartOf":{"@id":"https:\/\/timesnewsgroup.com.au\/themooraboolnews\/#website"},"primaryImageOfPage":{"@id":"https:\/\/timesnewsgroup.com.au\/themooraboolnews\/news\/pavilion-delays-cause-frustration\/#primaryimage"},"image":{"@id":"https:\/\/timesnewsgroup.com.au\/themooraboolnews\/news\/pavilion-delays-cause-frustration\/#primaryimage"},"thumbnailUrl":"https:\/\/static.timesnewsgroup.com.au\/prod\/uploads\/sites\/28\/2022\/08\/website-640x480-1.jpg","datePublished":"2022-08-17T22:00:20+00:00","dateModified":"2024-02-02T11:12:50+00:00","breadcrumb":{"@id":"https:\/\/timesnewsgroup.com.au\/themooraboolnews\/news\/pavilion-delays-cause-frustration\/#breadcrumb"},"inLanguage":"en-AU","potentialAction":[{"@type":"ReadAction","target":["https:\/\/timesnewsgroup.com.au\/themooraboolnews\/news\/pavilion-delays-cause-frustration\/"]}]},{"@type":"ImageObject","inLanguage":"en-AU","@id":"https:\/\/timesnewsgroup.com.au\/themooraboolnews\/news\/pavilion-delays-cause-frustration\/#primaryimage","url":"https:\/\/static.timesnewsgroup.com.au\/prod\/uploads\/sites\/28\/2022\/08\/website-640x480-1.jpg","contentUrl":"https:\/\/static.timesnewsgroup.com.au\/prod\/uploads\/sites\/28\/2022\/08\/website-640x480-1.jpg","width":640,"height":480,"caption":"Ballan Recreation Reserve works have come to a halt, before they have really started. Photo - Lachlan Ellis"},{"@type":"BreadcrumbList","@id":"https:\/\/timesnewsgroup.com.au\/themooraboolnews\/news\/pavilion-delays-cause-frustration\/#breadcrumb","itemListElement":[{"@type":"ListItem","position":1,"name":"Home","item":"https:\/\/timesnewsgroup.com.au\/themooraboolnews\/"},{"@type":"ListItem","position":2,"name":"Pavilion delays cause frustration"}]},{"@type":"WebSite","@id":"https:\/\/timesnewsgroup.com.au\/themooraboolnews\/#website","url":"https:\/\/timesnewsgroup.com.au\/themooraboolnews\/","name":"The Moorabool News","description":"","publisher":{"@id":"https:\/\/timesnewsgroup.com.au\/themooraboolnews\/#organization"},"potentialAction":[{"@type":"SearchAction","target":{"@type":"EntryPoint","urlTemplate":"https:\/\/timesnewsgroup.com.au\/themooraboolnews\/?s={search_term_string}"},"query-input":{"@type":"PropertyValueSpecification","valueRequired":true,"valueName":"search_term_string"}}],"inLanguage":"en-AU"},{"@type":"Organization","@id":"https:\/\/timesnewsgroup.com.au\/themooraboolnews\/#organization","name":"The Moorabool News","url":"https:\/\/timesnewsgroup.com.au\/themooraboolnews\/","logo":{"@type":"ImageObject","inLanguage":"en-AU","@id":"https:\/\/timesnewsgroup.com.au\/themooraboolnews\/#\/schema\/logo\/image\/","url":"https:\/\/static.timesnewsgroup.com.au\/prod\/uploads\/sites\/28\/2024\/01\/MooraboolNews-logo.png","contentUrl":"https:\/\/static.timesnewsgroup.com.au\/prod\/uploads\/sites\/28\/2024\/01\/MooraboolNews-logo.png","width":1089,"height":400,"caption":"The Moorabool News"},"image":{"@id":"https:\/\/timesnewsgroup.com.au\/themooraboolnews\/#\/schema\/logo\/image\/"}},{"@type":"Person","@id":"https:\/\/timesnewsgroup.com.au\/themooraboolnews\/#\/schema\/person\/bfbc5a1c6baaf34dd181f21c64f18302","name":"Lachlan Ellis","image":{"@type":"ImageObject","inLanguage":"en-AU","@id":"https:\/\/secure.gravatar.com\/avatar\/4b8766ff6263c9ffb6ec80f89efea9b7a992bc23f7fd86445d569b0e6b510f3e?s=96&d=mm&r=g","url":"https:\/\/secure.gravatar.com\/avatar\/4b8766ff6263c9ffb6ec80f89efea9b7a992bc23f7fd86445d569b0e6b510f3e?s=96&d=mm&r=g","contentUrl":"https:\/\/secure.gravatar.com\/avatar\/4b8766ff6263c9ffb6ec80f89efea9b7a992bc23f7fd86445d569b0e6b510f3e?s=96&d=mm&r=g","caption":"Lachlan Ellis"},"url":"https:\/\/timesnewsgroup.com.au\/themooraboolnews\/author\/lachlanellis\/"}]}},"_links":{"self":[{"href":"https:\/\/timesnewsgroup.com.au\/themooraboolnews\/wp-json\/wp\/v2\/posts\/11286","targetHints":{"allow":["GET"]}}],"collection":[{"href":"https:\/\/timesnewsgroup.com.au\/themooraboolnews\/wp-json\/wp\/v2\/posts"}],"about":[{"href":"https:\/\/timesnewsgroup.com.au\/themooraboolnews\/wp-json\/wp\/v2\/types\/post"}],"author":[{"embeddable":true,"href":"https:\/\/timesnewsgroup.com.au\/themooraboolnews\/wp-json\/wp\/v2\/users\/221"}],"replies":[{"embeddable":true,"href":"https:\/\/timesnewsgroup.com.au\/themooraboolnews\/wp-json\/wp\/v2\/comments?post=11286"}],"version-history":[{"count":0,"href":"https:\/\/timesnewsgroup.com.au\/themooraboolnews\/wp-json\/wp\/v2\/posts\/11286\/revisions"}],"wp:featuredmedia":[{"embeddable":true,"href":"https:\/\/timesnewsgroup.com.au\/themooraboolnews\/wp-json\/wp\/v2\/media\/25815"}],"wp:attachment":[{"href":"https:\/\/timesnewsgroup.com.au\/themooraboolnews\/wp-json\/wp\/v2\/media?parent=11286"}],"wp:term":[{"taxonomy":"category","embeddable":true,"href":"https:\/\/timesnewsgroup.com.au\/themooraboolnews\/wp-json\/wp\/v2\/categories?post=11286"},{"taxonomy":"post_tag","embeddable":true,"href":"https:\/\/timesnewsgroup.com.au\/themooraboolnews\/wp-json\/wp\/v2\/tags?post=11286"},{"taxonomy":"post_folder","embeddable":true,"href":"https:\/\/timesnewsgroup.com.au\/themooraboolnews\/wp-json\/wp\/v2\/post_folder?post=11286"}],"curies":[{"name":"wp","href":"https:\/\/api.w.org\/{rel}","templated":true}]}}